South Claiborne Avenue Overpass from Tulane Avenue east bound, showing Cleveland Street on-ramp Attached text: Rapidly approaching completion is the section of Interstate 10 from Orleans Avenue to Tulane Avenue. This project of the State Highway Department, costing $7.2 million, is scheduled to be opened to traffic in mid-May of this year.